Question reference: S6W-27060

  • Date lodged: 25 April 2024
  • Current status: Answered by Fiona Hyslop on 7 May 2024

Question

To ask the Scottish Government when the next routine maintenance is scheduled to be carried out on each junction of the A9 between Perth and Inverness.


Answer

Programmes of routine maintenance on all trunk roads are developed based on need and are delivered on a prioritised based within the limits of available funding. On occasion other programmes of work, for example road safety, may recommend works that upgrade trunk road signage and road markings.

A number of schemes have been completed on the recently through this budget as part of a package of short term works to improve safety prior to the dualling of the remainder of the A9. Cyclic maintenance is also carried out across trunk roads. This work including grass cutting at junctions to keep visibility splays clear and bollard cleaning to maintain their reflectivity.

The following list highlights a diverse range of schemes currently being prepared for the A9:

  • A9 Pitlochry Hospital signs – sign renewal in advance of the southbound off slip and the northbound off slip to Pitlochry. This work is provisionally programmed between 29-04-24 and 03-05-24.
  • A9 Inshes countdown signs – replacement of countdown marker signs in advance of the Inshes junction (northbound off slip). This work is provisionally programmed between 27-05-24 and 31-05-24.
  • A9 South of Bogbain junction ditching. This drainage work is provisionally programmed between 08-07-24 and 12-07-24.

Additional routine maintenance schemes may be developed and delivered this financial year. This will depend on feedback from weekly inspections and perceived need.